A LOT has happened this week!

they installed the forms to pour the new concrete footers

the plumber was here and removed the old sewer pipe and installed new ones (along wall instead of along floor)

they installed some water drainage system and started pouring concrete

just a few shots of around the property (including a lovely shot of the toilet that is still in our yard!) - you can click on pics to see them bigger




the removal of the walls around the entry and the steps down to the basement (they will dig farther back so the steps are not steep and then build new interior steps - this part of the house will be closed in soon)


Jon removed the balcony railing since the builders are arriving next week

and last and certainly my least favorite, is that we had to rip open the dining room wall yet again (3rd time better be a charm) to replace the sewer pipes up to the bathroom. This wall has to stay open until we are ready to demo the bathroom upstairs as the pipes have to be replaced up there and connected here. It's going to be a long couple of months!