Siding is on



Siding on the lower half is on - the shingles for the upper half came in on Friday and will go up early next week!

Sunday, July 24, 2011

We have a door!!!!


A lot has been happening in the last few days, but this is by far the most exciting!


Thursday, July 14, 2011

The Latest

Our contractor is almost done with the outside...we are just waiting for the door and siding to come in - it should be here late next week and then it will just take them a few days to finish everything up.

Meanwhile, a lot is happening inside...our house has been full of contractors...plumbers, electricians, hvac etc.

This is in the downstairs part of the addition off the kitchen. They have roughed in a closet for our laundry etc. and then the open space to the right is for a built in desk.



This is upstairs - what will be Anthony's room

and the kids bathroom:

Thursday, July 7, 2011

Roof & Windows!

they did such a fantastic job matching the roof - you can't tell the old (10 yrs.) from the new!


Tuesday, July 5, 2011

These guys are fast!

last Friday, a.m.


what they got done that day!


after another day of work today